海口:逾期半年未交房 开发商称因变压器未移走--亲稳网络舆情监控室
2012-08-10

  南海网海口7月19日消息(南海网见习记者吴湟帅)19日上午,海口市民贺女士向南海网反映,她于2010年在海口红城湖路一名为“时代佳园”的楼盘购买了套房子,当时开发商在合同上承诺交房时间为2012年1月份,可到规定日期后,开发商又告知自己,因天气原因交房日期延至4月份,可令贺女士纳闷地是,房子至今仍未交付,她曾多次上门讨说法都遭到商家推延。

South China sea nets haikou July 19 news(South China sea nets trainee reporter WuHuang handsome)19 morning,Ms royal haikou people to the south China sea nets reflect,She in 2010 in haikou city road called a red lake“Times good garden”Building a house to buy,When developers in the contract promised to pay for time in January 2012,But after the date to provisions,Developers and told myself,Because of the weather makes a room adjourned in April,Can make Mr Lady wonder is,The house has not been delivered,Many a time has she the door please statement were merchants delaying。

  

交房时间被一延再延 业主讨说法遭推脱 Make a room by a delay time to delay the owner for saying was to push to take off

  据贺女士介绍,在2010年她看中了位于红城湖路省烟草局对面的时代佳园小区,当时便跟商家签订合同,合同中清楚注明将于2012年1月交房。好不容易到了今年1月份,她满心欢喜的以为马上就可以住上购买的新房时,却意外地收到商家邮寄来的一封延期通知书,通知书上称去年底由于受暴雨影响,拖慢了工程的进展,需要等到今年4月份才能交房。

According to ms royal is introduced,In 2010 she considers the red lake city road across the province of YanCaoJu times good garden district,When he signed the contract with merchants,Indicate clearly in the contract will be in January 2012 makes a room。Very not easy to in January this year,She filled with joy to think that'll be live on purchase new house,Surprisingly received merchants came in the mail a letter postponed the notification,Notice that by heavy rains end of influence,Slow down the progress of the project,Need to wait until April to make a room。

  “起初我也以为是受去年底的暴雨影响,所以当时认为交房延期至4月份也情有可原。但没想到商家一再拖延,至今房子仍未交付。”贺女士郁闷地说到,到了今年4月份,她迟迟等不到商家通知交房的电话,便上门讨要说法。但每次商家都以不同的说法拖延,“这次说草坪没有铺好,下次说电线没有安装……每次都是说延迟10天交房。”

“At first I thought by the end of the heavy rains influence,So that was postponed to make a room in April also excusable。But didn't expect businessman has repeatedly delayed,So far the house has still not been paid。”Ms royal depressed to said,In April this year,She can make a room can notify the phone business,Then the door for claim。But every time the trade company with different versions of delay,“The "no the lawn,The next time said no installation...... wireEvery time is said delay 10 days to make a room。”

  此外,贺女士也从不少业主的口中得知,她们也同样遭到了商家以种种借口有意延迟交房。对于贺女士的困扰,律师则表示,如果根据当时合同上约定的交房日期,开发商已构成违约,购房者可按照合同约定要求开发商支付违约金。

In addition,Ms royal from many owner that the mouth,They also were the merchants with excuses to delay makes a room。Ms royal for the problems,Lawyer, said,If according to the contract agreed to pay at that time on the date,Developers have constituted a breach of contract,The person that buy a house can ask to develop business in accordance with the contract, pay a fine。

  

商家借故躲避采访 记者欲电话采访遭挂断 Businessmen used to avoid the reporters by telephone interviews hang up

  19日上午,南海网记者来到该小区售楼处,走进售楼处看到里面只有4名工作人员。当记者表明来意想采访商家,称有市民反映该小区存在借故延迟交房的问题。其中一名男子回答称售楼中心工作人员已经下班,有问题等下午有人上班再来采访。

19 morning,South China sea network reporter came to the district sales offices,Walked into the sales department see inside only four workers。When a reporter to interview businesses that intent,Says citizens reflect this village exist problems of making a room excuse delay。One man answer say center staff are off work,A problem and so on the afternoon of interviewing someone to work。

  随后,记者离开售楼大厅,到门外拨通了贺女士提供的相关负责人电话,可电话在接通后不到几秒便立即挂断,但还可以清楚的听到是里面那4名工作人员交流的声音。在电话挂断后不久,大厅内的2名工作人员就出来立即驾车离开。

then,The reporter from sales of the hall,The door of ms royal dialed provide the relevant person in charge of phone,Can phone in after connect within a few seconds immediately hang up,But can also clear of hear is inside that four work personnel exchanges of voice。In telephone hang up soon after,In the hall of the two workers went out driving out immediately。

  

有关负责人称“延迟交房因小区前变压器未移走所致” Officials say“Delay to pay for community not removed before transformer be caused by”

  下午,南海网记者再次来到该小区售楼中心看到,里面同样坐着4个人,但只有一名男子是上午在此处的工作人员。当记者问到售楼中心难道无人上班么?该名男子回答称,“小区的房子已经全部售完,现在售楼中心已经取消,如果市民有事可以找开发商。”

afternoon,South China sea nets journalist again this village center came to see,It also sit four people,But only a man is here in this morning's staff。When a reporter asked center is no one to work?The man answered says,“The house has all been sold out,Now center has been cancelled,If citizens have something can look for developers。”

  当记者问及该名男子的身份时,他表示自己只是该小区的物业工作人员。他还说,该小区延迟交房是有原因的,主要是去年强降雨影响了工程的进度,加上房地产萎缩,开发商的资金出现了点问题,所以才会出现延迟交房的情况。

When a reporter asked about the man's identity,He said he just this community property staff。He also said,This village delay to pay for a reason,Main is heavy rain last year affected the progress of the projects,With real estate atrophy,Developers funds appear a little problem,So just can appear delay to pay。

  该工作人员的解释是否属实?随后,记者以另一个电话号码拨通了贺女士提供的相关负责人电话。电话接通后,该陈姓相关负责人无奈地回答称,与顾客签合同确实是定在今年1月交房,但由于去年强降雨的影响,导致工程无法施工不得不延迟交房时间。随后,公司在铺草坪、以及相关水电时又遇到种种情况,因此不得不延迟交房。

The staff of the explanation is true?then,Reporter by another telephone number dialed ms royal provide the relevant person in charge of the phone。Phone after connect,The relevant person in charge of helplessly answer surnamed Chen says,Sign the contract with customers is indeed in January this year will make a room,But because of the influence of the heavy rain last year,Lead to engineering construction had to delay time cannot make a room。then,The company over the lawn、And related water and electricity again meet when of various circumstances,So had to delay makes a room。

  “我们小区前的变压器都向电力部门申请迁移一个月了,钱也汇了,但还是迟迟不见迁移,因此我们也很无奈。”陈先生说,由于其他部门工作进程慢,也间接影响了小区的整体装修,因此不得不延迟交房。

“Our village of transformer are before power department to apply for transfer for a month,The money also collected,But still not delayed migration,So we are helpless。”Mr. Chen said,Due to other department work in progress is slow,Also indirectly affects the district's whole decorates,So had to delay makes a room。