中吴大道修成了“瓶颈”大道 改造工程一拖再拖--亲稳网络舆情监测室
2012-08-18

  “中吴大道戚墅堰这段道路,7月初就通车了,为什么有一段路面只修一半?”近日,有网友和当地居民反映称,中吴大道天宁大桥至232省道段有一段200米长半幅未完工的路面以及电线杆未能迁移,造成该段道路通行“瓶颈”。对此,常州市政府有关部门解释称,造成该半幅路面未施工的主要原因是拆迁问题,征收拆迁结束后将立即组织施工

“WuDaDao in qishuyan this road,July is the traffic,Why have a road only taking half?”recently,Have net friend and local residents reflect says,In WuDaDao day better bridge to 232 provincial road section has a 200 m long half picture unfinished pavement and telegraph pole failed to transfer,The cause traffic“bottleneck”。this,Changzhou relevant government departments explanation says,That caused the half range is not the main cause of road construction is the problem,After the end of the collection will immediately organization construction。

  

读者反映 Readers reflect

  

路上有个200米长瓶颈 The road has a 200 m long bottleneck

  近日,有读者发帖称,中吴大道戚墅堰段在7月初通车了,可是从天宁大桥往东,有一段路面只修了一半,而且道路当中还有电线杆,“这算是什么工程?什么时候能到位?”

recently,Readers post said,WuDaDao qi shuyan period in early July in the traffic,But from the day better bridge to the east,There is a road only taking half,And of the road and telegraph pole,“This is what project?What time can you in place?”

  就网友反映的问题,记者来到现场采访。从天宁大桥下桥后往东,记者就看到道路北侧已经修好摊铺了沥青,车辆在路面上通行,但道路南半幅则尚未动工,路面满是土石和一些建筑垃圾,这些土石和建筑垃圾南侧则有一些房屋建筑。道路南半幅未修部分从天宁大桥到印莊桥约数百米。来往的车辆也都在北侧半幅道路上通行,一直过了印莊桥才改道正常行驶。由于只有半幅路面通车,原本通畅的道路在这里变得拥挤。

Will net friend reflects the problem,The reporter comes to a live interview。From the day better bridge after the bridge to the east,Reporters saw the north road has been repaired the paving asphalt,Vehicles in road traffic,But the road south half range is not start,The road is full of debris and some construction waste,These debris and construction waste the south there are some housing construction。Road south half range not fix partly from day better bridge to print ZhuangQiao about hundreds of meters。The traffic in the north of half way through,The seal has been ZhuangQiao just redirection normal running。Since there is only half of the road traffic,Originally unobstructed road become crowded in here。

  过了印莊桥再往前,记者发现道路两侧还有数十根旧电线杆“长”在沥青路面上,给车辆和行人带来很大不便。有的电线杆由于位置靠近路当中,半幅路面被占据掉了一半的机动车道。汽车和骑电瓶车的人到此处都要放慢速度小心翼翼。而道路靠近宋剑路附近,由于路面被一排多根电线杆占据,导致往西的车道变成了单向一车道。

After printing ZhuangQiao forward again,Reporter discovery of roadside and dozens of root old telegraph pole“long”In the asphalt,Give the vehicle and pedestrian brings great inconvenience。Some telephone poles because the position of road near,Half of the road taken off half of the motorway。Cars and ride battery car people here will slow down carefully。And the road near the SongJian road nearby,Because the road was a row of many wire pole occupy,Cause to the west lane into unidirectional a lane。

  附近的居民戴先生告诉记者,他们对这段道路的改造工程期盼已久,本来说是去年底就通车,后来因为梅港桥重建的原因,一直到今年7月初才可以通行,但是大家又发现天宁大桥到印莊桥还剩一边道路没施工,而且道路上那么多电线杆,都成为这段道路的“瓶颈”。“希望政府有关部门能早点解决这个问题,毕竟这是我们东边居民出行的一条主要通道。”记者在采访中,不少居民都赞同戴先生的说法。

Nearby residents Mr Dai told reporters,They to this section of road reconstruction project long-expected,Originally, the end is open to traffic,But for may harbor bridge reconstruction of reason,Until in early July this year can passage,But everyone again found that day better bridge to ZhuangQiao printed with side road no construction,And on the road so many telegraph pole,Have all become this section of the road“bottleneck”。“Hope the relevant government departments can solve the problem earlier,After all, this is our residents travel to the east of the main channel。”Reporter in the interview,Many people agree with Mr Dai said。

  

市政回应 Municipal response

  

拆迁工程一结束就施工 The end of a construction project

  就中吴大道天宁大桥至232省道段改扩建工程一事,常州市政府“每月一告”发布消息:在网友反映中吴大道戚区段改造工程施工质量差的帖文上,姚晓东市长批示:“请志军、玉清同志查核并即作必要整改完善。”经查,帖文中反映存在问题的路段为中吴大道天宁大桥印莊桥段。目前该路段南半幅尚未开工,所以造成帖文中反映的“电杆矗立在道路中央”的问题。造成该幅路面未施工的主要原因是,该路段上有一家电动工具厂因拆迁款问题迟迟不签署拆迁协议,导致拆迁工作停滞,工程无法实施。目前,相关拆迁工作正按属地管理原则,由戚墅堰区在加紧推进中。常州市建设局将在沿线征收拆迁工作结束后,立即组织该路段的施工。

Medium WuDaDao day better bridge to 232 provincial road section of the reconstruction,Changzhou government“Every month against”Said in a news release:In the net friend reflect WuDaDao qi section in the reconstruction project of the poor quality of construction for the text,YaoXiaoDong mayor instruction:“Please will army、Jade qing comrade check and make necessary improvement is perfect。”The basis of,1 this paper reflects the existing problems in the section for WuDaDao day better bridge print zhuang bridge。The road south half picture has not yet commenced,So this paper reflects the cause for“Pole stands in the road”problems。The picture is not caused by road construction is the main reason of the,This section has a electric tools factory because of the money problem has not signed the agreement,Lead to stagnation of demolition work,Engineering can not be implemented。At present,Related demolition work is press apanage management principle,By qi shuyan area in intensify in advance。Changzhou city construction bureau will impose along after the demolition work,Immediately organize the road construction。

  常州市市政工程管理处一位负责人告诉记者,该段未施工的南半幅道路长约200米。他还解释说,这条道路上的电线杆迁移改造工程,也只能等拆迁工作完成后才能实施。

Changzhou municipal engineering management a person in charge told reporters,The construction of the south not half of road is about 200 meters long。He also explained that,The path of telegraph pole migration reconstruction project,Also have to wait for the completed work to implement。